Steering Committee Sign-Off & Authority
Has the executive steering committee established formal decision rights and approved the gate criteria for cutover authorization?
An interactive, evidence-gated decision assessment evaluating your program across 30 authoritative controls in 8 core ERP domains. Separates assessment coverage from verified audit readiness, identifies active cutover blockers, and calculates an objective Steering Committee advisory.
Mandatory cutover controls have not been evaluated with objective evidence.
Executive authority, stakeholder sign-offs, statutory concurrence, and SI commitments.
Has the executive steering committee established formal decision rights and approved the gate criteria for cutover authorization?
Have all designated Business Process Owners formally approved their functional stream readiness for production operations?
Have internal audit, statutory compliance, and data privacy officers confirmed regulatory compliance controls?
Have the System Integrator (SI) and key software vendors submitted formal contractual delivery declarations?
Scenario execution rates, defect thresholds, regression verification, and performance benchmarks.
Were 100% of planned critical and high-priority end-to-end business process scenarios executed in UAT?
Are all critical (Sev-1) and high (Sev-2) defects resolved, or mitigated by approved business workarounds?
Have all defect fixes undergone verified regression testing without introducing secondary business process breaks?
Has the production-like environment demonstrated acceptable transaction response times under peak peak-hour loads?
Was an end-to-end cross-functional business simulation executed to validate cross-module handoffs?
Master data cleansing, trial balance reconciliation, open orders, and delta catch-up.
Have all production master data entities (Customer, Vendor, Material, Chart of Accounts) reconciled 100% against legacy extracts?
Do opening General Ledger balances and Subledger open items reconcile exactly to the signed legacy trial balance?
Have open purchase orders, sales backlog, and inventory balances reconciled accurately with documented cutover conversions?
Is the sequence and timing for legacy system transaction freeze and delta data capture fully verified and tested?
Interface connectivity, external bank/EDI verification, queue error handling, and sequencing.
Are all production middleware channels, API endpoints, and direct interfaces configured and connectivity-verified?
Have external financial institutions, EDI trading partners, and 3PL carriers validated production communication and file formats?
Have asynchronous message queue error handling, alerting thresholds, and replay mechanisms been validated?
Is the activation order of interfaces (pre-cutover freeze, cutover blackout, post-cutover unlock) aligned with data loading?
End-user training thresholds, role provisioning, SoD audit, SOP publication, and BCP fallback.
Have targeted business users completed mandatory role-based training and demonstrated system competency?
Are 100% of user production access accounts provisioned with zero unapproved Segregation of Duties conflicts?
Are updated business process SOPs and step-by-step desktop guides published and accessible to all operational staff?
Are interim manual business procedures documented for essential business processes if technical issues arise?
Master runbook baselines, full mock cutovers, Point of No Return (PONR), and transport freeze.
Does the detailed cutover schedule identify task durations, exact dependencies, and a single named owner per task?
Did at least one full mock cutover execute successfully within the planned production cutover window?
Has the technical Point of No Return been explicitly defined with a documented, tested legacy rollback procedure?
Has production environment configuration, parameter sizing, and transport freeze been enforced and locked?
24/7 support roster, daily defect triage cadence, war room, and monitoring alert systems.
Is a designated Level 1, 2, and 3 support organization staffed and scheduled across all operational shifts and timezones?
Are daily defect triage meetings, executive war room facilities, and priority escalation workflows established?
Are production server health, database thresholds, interface queues, and batch job monitors active with 24/7 alerts?
Pre-cutover exception risk ledger and formal executive committee voting authorization.
Have all 28 operational controls been assessed with objective evidence, and are all exceptions approved in the Risk Ledger?
Has the executive steering committee formally voted and executed the written Go/No-Go decision authorization record?
Evidence-grounded decision support across readiness scoring, source-verified advice, risk registers, zero-slack cutover critical paths, and drift assurance.
Weighted composite of readiness (35%), UAT pass rate (25%), cutover buffer (20%), and risk mitigation (20%).
Readiness exceeds 85% with zero open Sev-1 blockers. Cutover is conditionally approved pending formal Business Process Owner waiver sign-offs.
Readiness advanced +4% from previous rehearsal milestone with 2 fewer critical blockers.
Deterministic, rule-driven, source-grounded decision assistant. Ask practical questions regarding cutover governance, UAT quality gates, defect waivers, rollback thresholds, and SteerCo decisions. All answers are synthesized deterministically from verified platform guides with explainable citations, zero LLM hallucinations, and strict human Steering Committee decision authority.
5x5 Likelihood × Impact scoring with automatic SteerCo escalation triggers for critical blockers.
| ID | Category | Title | Owner | Raw | Residual | Status | Actions |
|---|---|---|---|---|---|---|---|
| RSK-001 | Data Migration | General Ledger opening balance trial balance discrepancy | Finance Lead | 12 (High) | 3 (Low) | MITIGATED |
Zero-slack critical path sequencing, resource overlap conflict detection, and rollback Point of No Return verification.
Grounded, consented benchmarking comparing internal program velocity against verified delivery audits. Get Go-Live Ready does not fabricate synthetic marketing percentiles.
Historical burn-down across 3 evaluated rehearsal milestones indicates readiness velocity is on track to achieve 95% target by scheduled Go-Live.
Comparison against 24 verified enterprise SAP S/4HANA manufacturing cutovers (Sample N=24, 95% CI). Your score (88%) aligns within standard deviation (±5.8%).
Evaluates control verification drift, stale test results, and expiring business sign-offs across assessment cycles.
| Assurance Check | Status | Audit Finding & Evidence Validity |
|---|---|---|
| Control Verification Drift | PASS | Zero verified controls have regressed to missing or partial status. |
| BPO Sign-Off Validity | PASS | Commercial & Financial BPO sign-offs recorded within valid 30-day window. |
| Data Reconciliation Freshness | PASS | Financial trial balance certificate signed 3 days ago (≤ 7 day cutover rule). |
Evaluation data, cutover runbooks, and defect notes are processed in client-side volatile memory. To guarantee tenant privacy, remote multi-tenant cloud persistence is gated.
Architectural Boundary: Get Go-Live Ready operates as a static-first platform deployed to Hostinger web roots. There is no server-side database (PostgreSQL/MySQL) or Node authentication daemon. Cloud storage is purposefully disabled to prevent accidental project custody risks.
Traditional project dashboards often report a single misleading "green" percentage based on task completion. This calculator strictly separates Assessment Coverage (whether a control has been evaluated) from Evidence-Verified Readiness (whether the checkpoint has objective audit artifacts verified by stream owners).
A 95% readiness score does not permit cutover if a single Critical control (such as general ledger opening trial balance reconciliation or disaster recovery rollback) is unverified. Any Critical control not marked Evidence Verified strictly forces a NO-GO ADVISORY.
A CONDITIONAL GO advisory is only generated when 100% of Critical controls are verified and remaining High-priority open items have formal business process owner sign-off and documented operational workarounds recorded in an Exception Risk Ledger.
This calculator provides evidence-based decision intelligence. It is not an automated authorization to execute cutover. Go-live authority resides exclusively with the executive project sponsor and voting members of the Executive Steering Committee.
These thresholds are tool-specific policies. Final go-live authorization belongs to the Steering Committee.
Formula: assessed applicable controls / total applicable controls × 100
Only valid Not Applicable exclusions are removed from the denominator.
Formula: evidence-verified controls / total applicable controls × 100
Assessment coverage and evidence-verified readiness are separate, unweighted percentages. A Not Applicable justification requires at least 10 characters.
With 30 total controls and 2 valid exclusions, there are 28 applicable controls. With 25 assessed controls and 22 evidence-verified controls, coverage is 89% (25 / 28 × 100) and verified readiness is 79% (22 / 28 × 100). Results are rounded to whole percentages.
Beyond isolated checklist evaluations, Get Go-Live Ready provides a continuous, source-grounded decision infrastructure integrating cross-stream governance, evidence verification, and cutover synchronizations.
Aggregates readiness scoring, UAT pass rates, cutover rehearsal buffer headroom, open Sev-1/2 defect counts, and active critical risks into a single executive Program Health Index and SteerCo Go/No-Go advisory.
Deterministic, rule-driven query engine grounded strictly in verified practitioner guides (GLR-G-001 through GLR-G-025). Provides explainable recommendations with verified citations and zero hallucination risk, maintaining human SteerCo authority.
Continuous 5x5 Likelihood x Impact operational risk scoring. Features residual risk mitigation tracking, critical risk blocker escalation (severity ≥ 20), and cycle detection preventing circular blocker deadlocks.
Synchronizes cutover task predecessor chains using Directed Acyclic Graph (DAG) dependency logic. Calculates zero-slack critical paths and monitors 72-hour weekend blackout window thresholds.
Ensures zero assessment data transmission to external servers. Supports local-first project persistence and export/import via tamper-evident .glrproj bundles verified with SHA-256 cryptographic hashes.
Enables empirical cohort comparisons against verified enterprise implementations (SAP S/4HANA Manufacturing, Retail, Financials, Oracle Fusion, Microsoft Dynamics 365) and tracks self-comparison milestone velocity.
Continuously monitors control drift, evidence artifact expiration, and blocker aging. Enforces multi-rehearsal variance tracking and mandatory technical rollback drill verification.
The ERP Go-Live Readiness Score Calculator evaluates enterprise delivery programs across 30 controls in 8 domains. It enforces a Zero Critical Blocker rule: if any critical control (such as general ledger opening balances or rollback recovery) is unverified, the engine issues an unconditional NO-GO advisory regardless of a high overall score.
Recommended Timing: Phase Gates (T-90, T-60, T-30, T-14, T-0 Cutover)
Integrate results into formal phase-gate deliverables, weekly program steering checkpoints, or the final 48-hour cutover countdown meeting.
๐ All inputs remain in local browser memory. Zero assessment data is transmitted to external servers.
Scenario: A multi-plant enterprise is 14 days from scheduled cutover. Delivery streams have evaluated 29 of 30 controls (1 excluded plant is marked Not Applicable). 26 controls are Evidence Verified, 2 are in progress, and 1 Critical control (DAT-02 Trial Balance Zero Delta) is unverified.
NO-GO ADVISORY. The system halts cutover approval due to unverified financial trial balance clearing. Remediation actions are prioritized in the action queue for immediate finance data lead execution.
The calculator enforces a Zero Critical Blocker safeguard: if any critical control (such as general ledger trial balance reconciliation, disaster recovery rollback, or open Sev-1 defect resolution) is unverified, the calculator strictly issues a NO-GO advisory regardless of overall percentage scores.
Assessment coverage measures the percentage of applicable controls that have been evaluated by delivery teams. Evidence-verified readiness measures the percentage of controls backed by verified audit artifacts signed off by accountable stream leads. The two metrics are tracked separately to prevent false confidence.
The Unified Decision Platform incorporates the 30-Control Readiness Calculator (GLR-09A), the Unified Readiness Dashboard (GLR-10A), the Evidence-Based Go-Live Decision Advisor (GLR-10B), the Continuous Risk Register (GLR-10C), Cutover Schedule Synchronization (GLR-10D), Local .glrproj Workspace (GLR-10E), Industry Benchmark Intelligence (GLR-10F), and Continuous Assurance (GLR-10G).
The advisor is a deterministic, rule-based recommendation engine grounded strictly in verified practitioner implementation guides. It classifies query intent and retrieves explainable guidance with exact guide citations, eliminating hallucination risks while leaving decision authority with the Steering Committee.
No. All calculations, scoring algorithms, advisor queries, risk registers, and PDF generation execute 100% locally in the user web browser memory. Project files use the tamper-evident .glrproj format with SHA-256 integrity validation and zero cloud data transmission.
This tool provides objective analytical models, deterministic calculations, and evidence-based decision guidance. It does not replace the formal voting procedures, fiduciary responsibilities, or risk authorizations of the project sponsor and Executive Steering Committee.